The
following set of charts are listed in order of design and construction
priorities developed to meet immediate needs and achieve the 2030
design. These priorities are based on projected population and traffic
demand.
Priority
1 items should begin immediately and includes such activities as
the improvement of intersections that are currently at Level of
Service F (Ideally, all roadways should operate at Level of Service
D or better). Priority 2 items should begin soon and include such
items as improvement of intersections that may become Level of Service
F within the near future.
Priorities
3-8 are based on traffic and population projections and may have
to be reevaluated as more of the land is developed. By priority
6, all of the improvements necessary through 2030 are expected to
be complete. Priorities 7 and 8 are broken up into a planning phase
and a construction phase. The team expects these phases to be necessary
by the time the Houghton Road corridor area is completely built
out.
Priority 1*
|
Action
Item
|
Location
|
Comments
|
|
Environmental
Assessment & Design Concept Report (DCR)
|
Houghton Rd
from Dawn Rd to Old Vail Rd
|
To include
bridge selection reports for the I-10 overpass and UPRR overpass
(accelerate the UPRR bridge selection)
|
|
Design/Construction
|
Houghton Rd
& Irvington Rd
Craycroft Rd & Golf
Links Rd
Kolb Rd & Golf Links
Rd
|
Signalize
the Irvington intersection
|
|
Design/Construction
|
UPRR Bridge
|
Bridge to
be replaced with 6 lanes or allow for future twin structure
|
|
Traffic Studies
|
Kolb Rd &
Golf Links Rd
Craycroft Rd & Golf
Links Rd
Houghton Rd & Irvington
Rd
Houghton Rd & Old
Vail Rd
Houghton Rd & I-10
Ramps
|
Intersection
studies (accelerate Irvington, Craycroft and Kolb studies)
|
|
Traffic Impact
Analyses
|
Adjacent to
any new development
|
Require developers
to participate in corridor improvements
|
|
Right-of-Way
Acquisition
|
Kolb Rd &
Golf Links Rd
Craycroft Rd & Golf
Links Rd
Houghton Rd & Irvington
Rd
Houghton Rd & Old
Vail Rd
UPRR Bridge area
|
Studies and
Design Concept Reports to define specific right-of-way acquisition
necessary
|
*Note: This work must be started immediately.
Intersections noted for construction are currently at Level of
Service F.
Priority 2
|
Action
Item
|
Location
|
Comments
|
|
Additional
Study
|
Area Arterial
Study
|
Study roadway
network north of I-10
|
|
Design/Construction
|
Houghton Rd
& Old Vail Rd
Houghton Rd & I-10
Ramps
|
Signalize
the three intersections with Houghton Road
|
|
Design/Construction
|
Houghton Rd
& Speedway Blvd
Houghton Rd & Broadway
Blvd
Houghton Rd & 22nd
St
Houghton Rd & Escalante
Rd
Houghton Rd & Drexel
Rd
Houghton Rd & Valencia
(northbound)
|
Add right
turn lanes at all of these major intersections. Most of them
are signalized.
|
|
EA & Design
Concept Report (DCR)
|
Houghton Rd
from Escalante Rd to Broadway Blvd
|
|
|
Traffic Studies
|
Houghton Rd
& Broadway Blvd
Houghton Rd & 22nd
St
Houghton Rd & Old
Spanish Trail
Houghton Rd & Golf
Links Rd
Houghton Rd & Escalante
Rd
|
Intersection
studies
|
|
Traffic Impact
Analyses
|
Adjacent to
any new development
|
Require developers
to participate in corridor improvements
|
|
Right-of-Way
Acquisition
|
Realigned
Houghton Rd at I-10
Major Intersections
from Escalante Rd to Broadway Blvd
Segment 1 Houghton Greenway
|
Studies and
DCRs to define specific right-of-way acquisition necessary
|
Priority 3
|
Action
Item
|
Location
|
Comments
|
|
Design/Construction
|
I-10 Interchange
|
To include
structure to 6-lane width
|
|
Design/Construction
|
Roadway from
Escalante Rd to Broadway Blvd
Roadway from Dawn Rd
to Old Vail Rd
|
Roadways using
4-lane interim typical section
|
|
Environmental
Assessments & Design Concept Reports
|
Houghton Rd
from Old Vail Rd to Escalante Rd
Golf Links Rd from Harrison
Rd to Houghton Rd
Golf Links/Alvernon/Aviation
Interchange
|
To include
bridge selection report for Pantano Wash bridge
|
|
Traffic Studies
|
Houghton Rd
& Rita Rd
Houghton Rd & Valencia
Rd
Houghton Rd & Poorman
Rd
Houghton
Rd & Drexel Rd
|
Intersection
studies
|
|
Traffic Impact
Analyses
|
Adjacent to
any new development
|
Require developers
to participate in corridor improvements
|
|
Right-of-Way
Acquisition
|
Realigned
Houghton Rd at Pantano Bridge
Major Intersections
from Old Vail Rd to Escalante Rd
Golf Links/Alvernon/Aviation
Interchange
Segment 2 Houghton Greenway
|
Design Concept
Reports to define specific right-of-way acquisition necessary
|
Priority 4
|
Action
Item
|
Location
|
Comments
|
|
Design/Construction
|
Pantano Wash
Bridge and
Houghton Rd from Escalante
Rd to Old Vail Rd
|
To include
structure to 6-lane width and roadways using 4-lane interim
typical section
|
|
Design/Construction
|
Interim Golf
Links/ Alvernon/ Aviation Interchange
Golf Links Rd from Harrison
Rd to Houghton Rd
|
Interim interchange
improvements
Golf Links to be increased
to 6 lanes
|
|
Environmental
Assessment & Design Concept Report
|
Houghton Rd
from Broadway Blvd to Tanque Verde Rd
|
To include
bridge selection reports for Agua Caliente and Tanque Verde
Wash bridges
|
|
Traffic Studies
|
Houghton Rd
& Speedway Blvd
Houghton Rd & Tanque
Verde Rd
|
Intersection
studies
|
|
Traffic Impact
Analyses
|
Adjacent to
any new development
|
Require developers
to participate in corridor improvements
|
|
Right-of-Way
Acquisition
|
Realigned
Houghton Rd at Agua Caliente and Tanque Verde Bridges
Major Intersections
from Broadway Blvd to Tanque Verde Rd
|
Design Concept
Reports to define specific right-of-way acquisition necessary
|
Priority 5
|
Action
Item
|
Location
|
Comments
|
|
Design/Construction
|
Houghton
Rd from I-10 to Old Spanish Trail
|
Including
roadway using 6-lane 2030 typical section
|
|
Design/Construction
|
Houghton Rd
from Old Spanish Trail to Tanque Verde Rd
|
Including
twin bridge structures at Agua Caliente and Tanque Verde Wash
crossings and roadway using 4-lane 2030 typical section
|
|
EA’s &
DCR’s
|
Houghton Rd
from Dawn Rd to Sahuarita Rd
I-10 Directional Ramp
|
To
include bridge selection report for directional ramp
|
|
Traffic Studies
|
Houghton Rd
& Sahuarita Rd
Houghton Rd & Sahuarita
Corridor
Houghton Rd & Dawn
Rd
Houghton Rd & Old
Vail Rd
Houghton Rd & Valencia
Rd
|
Intersection
studies
|
|
Traffic Impact
Analyses
|
Adjacent to
any new development
|
Require developers
to participate in corridor improvements
|
|
Right-of-Way
Acquisition
|
I-10 Directional
Ramp
Major Intersections
from Sahuarita Rd to Dawn Rd
Segment 3 Houghton Greenway
|
Design Concept
Reports to define specific right-of-way acquisition necessary
|
Priority 6 *
|
Action
Item
|
Location
|
Comments
|
|
Design/Construction
|
Houghton
Rd from Dawn Rd to Sahuarita Rd
|
Including
roadway using 4-lane 2030 typical section
|
|
Design/Construction
|
Houghton
Rd & Valencia Rd
Houghton Rd &
Old Vail Rd
|
Grade-separated
interchanges with single point urban interchanges
|
|
Design/Construction
|
NB Houghton
Rd to WB I-10 Directional Ramp
|
Paving and
bridge structure
|
|
Traffic
Impact Analyses
|
Adjacent
to any new development
|
Require
developers to participate in corridor improvements
|
*Note:
Completion of improvements through this priority meet projected
2030 corridor traffic projection needs.
Priority 7
Action Item
|
Location
|
Comments
|
|
Houghton Road
Corridor Study
|
Houghton Rd
from Sahuarita Rd to Tanque Verde Rd
|
Update this
study
|
|
Environmental
Assessment and Design Concept Report
|
Golf Links/Alvernon/Aviation
Fully Directional Interchange
|
Including
bridge selection reports and traffic reports
|
|
Environmental
Assessments and Design Concept Reports
|
All segments
on Houghton Rd from Sahuarita Rd to Tanque Verde Rd
|
Including
bridge selection reports and traffic reports
|
|
Traffic Impact
Analyses
|
Adjacent to
any new development
|
Require developers
to participate in corridor improvements.
|
|
Right-of-Way
Acquisition
|
Golf Links/Alvernon/Aviation
|
Design Concept
Report to define specific right-of-way acquisition necessary
|
Priority 8
|
Action
Item
|
Location
|
Comments
|
|
Construction
|
Golf Links/Alvernon/Aviation
|
System Interchange
|
|
Construction
|
Houghton Rd
& Valencia Rd and Houghton Rd & I-10
|
System interchanges
|
|
Construction
|
Houghton Rd
& Old Spanish Trail and all mile intervals on Houghton
Rd from Golf Links Rd to Sahuarita Rd
|
Grade-separated
interchanges
|
|
Construction
|
Houghton Rd
from Sahuarita Rd to I-10 and from Old Spanish Trail to Tanque
Verde Rd
|
Widen to 6
lanes.
|
|
Traffic Impact
Analyses
|
Adjacent to
any new development
|
Require developers
to participate in corridor improvements
|
|